This list of seismically-isolated buildings and other structures in the United States has been developed by the Protective Systems Research Group of the Earthquake Engineering Research Center at the University of California at Berkeley. The list was last updated in May 1997. We welcome any comments or additions to this list so that we can keep it up to date. For instructions, please go to our feedback page.

Seismically Isolated Buildings and Other Structures in the United States
No.
Name
Location
Owner
Engineer
Contractor
Super- Structure
Eq. Design Spectrum
Isolation System/ Supplier
Remarks
1Foothill Communities Law & Justice Center
New, 1985
Rancho Cucamonga, CACounty of San BernardinoTaylor & Gaines; Reid & TaricsMcCarthy/ Obayashi230,000 sq.ft. 4-story steel-98 HDR (LTV)-
2Standford Linear Accelerator Center Mark II Detector
Retrofit, 1987
Menlo Park, CAStandford Linear Accelerator Center--3 million pound Mark II DetectorDBE A = 0.6g S14 LRB
(DIS/Furon)
-
3Evans & Sutherland Building 600
New, 1988
Salt Lake City, UtahThe Evans & Sutherland Corp.Reaveley Engineers & Assoc.The Bettilyon Corp.190,000 sq.ft. 4-story steelDBE A = 0.25g S140 LRB
58 NRB (DIS/Furon)
-
4Standford Linear Accelerator Center Mark II Detector
New, 1988
Menlo Park, CAStandford Linear Accelerator Center--1.3 million pound CalorimeterDBE A = 0.6g NRC4 LRB (DIS/Furon)It was necessary to provide seismic integrity while on its temporary support structure during assembly.
5Salt Lake City and County Building,
Retrofit, 1989
Salt Lake City, UtahSalt Lake City CorporationE.W Allen & AssociatesJacobsen Constr=2E170,000 sq.ft. 5-story unreinforced brick & sandstoneDBE A = 0.2g S2208 LRB
239 NRB (DIS/Furon)
The base structure is topped off with a clock tower that exceeds 250 ft=2E in height.
6Fire Command and Control Center
New, 1990
East Los Angeles, CACounty of Los AngelesFluor-Daniel Engineers, Inc.Fluor-Daniel Engineers, Inc.32,000 sq.ft. 2-story steel-32 HDR (Fyfe Assoc., Dynamic Rubber)-
7USC University Hospital
New, 1991
Los Angeles, CANational Medical Enterprises, Inc.KPFF Consultng Engineers, Inc.J.A. Jones Construction Co.350,000 sq.ft. 7-story steelDBE A = 0.4g S168 LRB
81 NRB (DIS/Furon)
-
8Rockwell International Corporate Headquarters (Building 80)
Retrofit, 1991
Seal Beach, CARockwell InternationalEnglekirk & Sabol, Inc.Morley Construction260,000 sq.ft. 8-story concreteDBE A = 0.55g S152 LRB
26 NRB (DIS/Furon)
-
9Marina Apartment
Retrofit, 1991
San Francisco, CADr. HawleyEPS-20,000 sq.ft.-31 FPS (EPS)-
10Kaiser Permanente Regional Data Center
New, 1992
Corona, CAKaiser Permanente FoundationTaylor & GainesTurner Construction Company120,000 sq.ft. 2-story steelDBE A = 0.6g S126 LRB
28 NRB (DIS/Furon)
-
11Two Residences
New, 1992
West Los Angeles, CADavid LoweDavid Lowe-4,700 sq.ft. ea.-GERB Resistant Base (GERB)-
12Titan Solid Rocket Motor Storage
1992
Vandenburg Air force Base, CAU.S. Air ForceBechtel National, Inc.-N/A-HDR (LTV)-
13Portland Water Bureau Water Control Center
New, 1993
Portland, OregonPortland Water BureauHarris Group, Inc.Koll Construction14,000 sq.ft. 2-story steelDBE A = 0.3g S131 LRB
4 NRB (DIS)
-
14Campell Hall
Retrofit, 1993
Monmouth, ORWestern Oregon State CollegeVan Domele, Looijenga, McGarrigle, KnaufColamette Construction Co.30,000 sq.ft. 3-story unreinforced masonryDBE A = 0.3g S126 LRB
16 NRB (DIS)
-
15Mackay School of Mines
Retrofit, 1993
Reno, NevadaUniversity of Nevada, RenoJack Howard & Assoc.; BIC-27,000 sq.ft.-HDR, Sliding bearings (Furon)-
16Emergency Operations Center
New, 1994
Los Angeles, CACounty of Los AngelesDMJM-33,000 sq.ft.-28 HDR (Bridgestone)-
17Traffic Management Center
New, 1994
San Diego, CACaltrans/CHPForell/Elsesser-45,000 sq.ft.-44 HDR (Bridgestone)-
18Hughes Building S-12
Retrofit, 1994
El Segundo, CAHughes Aircraft CompanyBrian L. Cochran AssociatesMorley Construction Co.240,000 sq.ft. 12-storyDBE A = 0.32g S224 LRB
21 NRB (DIS)
-
19Oakland City Hall
Retrofit, 1994
Oakland, CACity of OaklandForell/Elsesser Engineers, Inc=2EOveraa/Miller153,000 sq.ft. 18-story steelDBE A = 0.48g S242 LRB
69 NRB (DIS)
-
20U.S. Court of Appeals
Retrofit, 1994
San Francisco, CAU.S. General Services AdministrationSkidmore, Owings & Merril-350,000 sq.ft.-256 FPS (EPS)-
21San Francisco Main Library
New, 1995
San Francisco, CAThe City of San Francisco Bureau of ArchitectureOlmm Structural DesignHuber, Hunt & Nichol, Inc377,000 sq.ft. 7-story steelDBE A = 0.48g S2LRB (DIS/Furon)-
22Martin Luther King/Drew Trauma Center
New, 1995
Los Angeles, CALos Angeles CountyJohn A. Martin & Assoc.Turner Construction Company75,000 sq.ft. 6-story DBE A = 0.55g S270 HDR (DIS/Furon)-
23AutoZone Headquarters
New, 1995
Memphis, Tenn.AutoZone CorporationJMGR, Inc. Structural DivisionInman Construction Corp.210,000 sq.ft, 8-story concrete DBE A = 0.16g S224 LRB
19 NRB (DIS)
-
24Long Beach V.A. Hospital
Retrofit, 1995
Long Beach, CADepartment of Veterans AffairsNabih Youssef & AssociatesDillingham Construction350,000 sq.ft. 12-story R.C.DBE A = 0.6g S1110 LRB
18 NRB (DIS/Furon)
-
25Missouri Botanical Garden Research Center
New, 1996
St. Louis, MO-Dames & Moore-4-story steel frame-44 HDR (Skellerup)-
26Kerckhoff Hall
Retrofit, 1996
UCLA Campus, Los Angeles, CAUCLABrandow & Johnston Assoc.Ray Wilson Company92,000 sq.ft. 6-story R.C./BrickDBE A = 0.6g S133 LRB
93 NRB (DIS/Furon)
-
27Hayward City Hall
New, 1997
Hayward, CACity of HaywardKPFF Consultng Engineers, Inc.DRR100,000 sq.ft.-53 FPS (EPS) 15 Viscous Dampers (Taylor)-
28San Bernardino County Medical Center
New, 1997
Colton, CASan Bernardino CountyKPFF Consulting EngineersJCM Group1,000,000 sq.ft. steelDBE A = 0.7g S2400 HDR (DIS) 186 Viscous Dampers (Taylor)A total of five buildings are included on the campus.
29Washigton State E.O.C.
New, 1998 (est.)
Camp Murray, WA-----FPS (EPS)-
30Public Safety Bldg.
New, 1998 (est.)
Berkeley, CA-OlmmN/ASteel frame-N/A-
31San Francisco Airport International Terminal
New, 1998
San Francisco, CA-Skidmore, Owings & MerrilHerrick/PDM1.6 million sq.ft.-272 FPS (EPS)20 in. dis. capacity 6% dyn. friction 3 sec. period
32San Francisco 911
New, 1998 (est.)
San Francisco, CA-Forell/Elsesser Engineers, Inc.S.J. AmorosoSteel frame-HDR (BTR/Andre)-
33San Francisco City Hall
Retrofit, 1998 (est.)
San Francisco, CACity & County of San FranciscoForell/Elsesser Engineers, Inc.Huber Hunt & Nichol, Inc.550,000 sq.ft. 5-storyDBE A = 0.5g S2530 LRB (DIS)-
34Los Angeles City Hall
Retrofit, 1999 (est.)
Los Angeles, CACity of Los AngelesN. Youssef & Assoc./ SIELehrer McGovern & Bovis912,000 sq.ft.-approx. 450 HDR, approx. 70 Sliding bearings (Bridgestone), approx. 70 viscous dampers (Taylor)Viscous dampers are also used in the isolation system and at one level of the tower superstructure.
35LAC + USC Medical Center
New, 2000 (est.)
East Los Angeles, CACounty of Los AngelesKPFFTurner Construction Company550,000-150 HDR (BTR/Andre)Under redesign due to project budget cutbacks
36Asian Art Museum
Retrofit, Planned
San Francisco, CACity & County of San FranciscoForell/Elsesser-170,000 sq,ft.-System not yet selected-
37Channing House
Retrofit, Planned
Palo Alto, CAChanning HouseRinne & PetersonAnderson Pacific Engin. Constr.260,000sq.ft. 11-story R.C.DBE A = 0.55g S256 LRB
56 NRB (DIS/Furon)
-
38Seattle Standpipe & Water Tank
Planned
Seattle, WashingtonSeattle Water DepartmentCygna Group Inc. (ICF Kaiser)-6 million and 2 million gallon water tanks-(System: N/A)-
FPS = friction pendulum system
HDR = high damping rubber
LRB = lead-rubber bearing